California's bullet train is hurtling toward a multibillion-dollar overrun, a confidential federal report warns
California’s bullet train could*cost taxpayers 50% more than estimated — as much as $3.6 billion more. And that’s just for the first 118 miles through the Central Valley, which was*supposed to be the easiest part of the route between Los Angeles and San Francisco.
A confidential Federal Railroad Administration risk analysis, obtained by The Times, projects that building bridges, viaducts, trenches and track from Merced to Shafter, just north of Bakersfield,*could*cost*$9.5 billion to $10 billion, compared with*the original budget of $6.4 billion.
The federal document outlines far-reaching management problems: significant delays in environmental planning, lags in processing invoices for federal grants and continuing failures to acquire needed property.*
The California High-Speed Rail Authority originally anticipated completing the Central Valley track by this year, but the federal risk analysis estimates that that won’t happen until 2024, placing the project seven years behind schedule.
The report, the most critical official assessment of the project to surface so far, is labeled a “confidential-draft deliberative document for internal use only” and*was*presented by senior Federal Railroad Administration executives to*California rail authority board Chairman Dan Richard and Chief Executive Jeff Morales on Dec. 1 in Washington.
This analysis puts the state on notice that it could face bigger cost overruns than anticipated and much longer delays than*have been made public, a troubling critique by an agency that has been a stalwart supporter and longtime financier of the nation’s largest infrastructure project.
Morales cautioned in an interview that the numbers in the analysis are only projections and estimates that do not account for intervention by the rail authority, and he asserted that the construction in the Central Valley will cost less than the risk analysis indicates. The estimates, he said, are based on a lot of assumptions that the authority wants to ensure*are correct.
“The point of doing this analysis is to identify the challenges and work through them,” he said. “They are not conclusions and not findings.”
The Federal Railroad Administration is tracking the project because it has extended $3.5 billion in two grants to help build the Central Valley segment. The administration has an obligation to ensure*that the state complies with the terms, including a requirement that the state has the funding to match the federal grants.*
Rep. Jeff Denham (R-Turlock), chairman of the House rail subcommittee, said Friday he would conduct an oversight hearing in the near future and fight any further federal funding.
“Despite past issues with funding this boondoggle, we were repeatedly assured in an August field hearing that construction costs were under control,” he said in a statement. “They continue to reaffirm my belief that this is a huge waste of taxpayer dollars.”
The railroad administration’s*analysis shows that the state*
http://www.latimes.com/local/california/la-me-bullet-cost-overruns-20170106-story.html
(article was a b*tch to copy and paste so only got half of it posted)
California's bullet train is hurtling toward a multibillion-dollar overrun, a confidential federal report warns
California’s bullet train could*cost taxpayers 50% more than estimated — as much as $3.6 billion more. And that’s just for the first 118 miles through the Central Valley, which was*supposed to be the easiest part of the route between Los Angeles and San Francisco.
A confidential Federal Railroad Administration risk analysis, obtained by The Times, projects that building bridges, viaducts, trenches and track from Merced to Shafter, just north of Bakersfield,*could*cost*$9.5 billion to $10 billion, compared with*the original budget of $6.4 billion.
The federal document outlines far-reaching management problems: significant delays in environmental planning, lags in processing invoices for federal grants and continuing failures to acquire needed property.*
The California High-Speed Rail Authority originally anticipated completing the Central Valley track by this year, but the federal risk analysis estimates that that won’t happen until 2024, placing the project seven years behind schedule.
The report, the most critical official assessment of the project to surface so far, is labeled a “confidential-draft deliberative document for internal use only” and*was*presented by senior Federal Railroad Administration executives to*California rail authority board Chairman Dan Richard and Chief Executive Jeff Morales on Dec. 1 in Washington.
This analysis puts the state on notice that it could face bigger cost overruns than anticipated and much longer delays than*have been made public, a troubling critique by an agency that has been a stalwart supporter and longtime financier of the nation’s largest infrastructure project.
Morales cautioned in an interview that the numbers in the analysis are only projections and estimates that do not account for intervention by the rail authority, and he asserted that the construction in the Central Valley will cost less than the risk analysis indicates. The estimates, he said, are based on a lot of assumptions that the authority wants to ensure*are correct.
“The point of doing this analysis is to identify the challenges and work through them,” he said. “They are not conclusions and not findings.”
The Federal Railroad Administration is tracking the project because it has extended $3.5 billion in two grants to help build the Central Valley segment. The administration has an obligation to ensure*that the state complies with the terms, including a requirement that the state has the funding to match the federal grants.*
Rep. Jeff Denham (R-Turlock), chairman of the House rail subcommittee, said Friday he would conduct an oversight hearing in the near future and fight any further federal funding.
“Despite past issues with funding this boondoggle, we were repeatedly assured in an August field hearing that construction costs were under control,” he said in a statement. “They continue to reaffirm my belief that this is a huge waste of taxpayer dollars.”
The railroad administration’s*analysis shows that the state*
http://www.latimes.com/local/california/la-me-bullet-cost-overruns-20170106-story.html